MPV architecture

Jardín de niños Cuautitlán

State of Mexico (MX)

PRECEDENT & PROPOSAL

A kindergarten and nursery located in Cuautitlán, with morning and afternoon shifts, required more space to develop all the activities that students, parents and educators perform daily.


The reconfiguration of the existing classrooms and toilets on the ground floor was the first thing to do. Thereafter, the extension of the building through a second floor.

PROGRAMME

The second floor includes the new principal's office and the multipurpose room where activities such as nap time and homework club are held. In addition to the dining room, staff toilet and warehouse.

PROCESS

· Excavation and placement of new footings and rebars

· Demolition of wall and column in classroom for expansion

· New beams on the ground floor to reinforce

· Walls of second floor and rebars casting

· Beams formwork and casting

· Slab formwork, assembly and casting

· Stucco on exterior walls

· Plastering and painting of internal walls

· Slab formwork removal

· Placement of windows and doors

· Tile installation

New footings | demolition and excavation

New footings | excavation

New footings | rebar in foundation

New footings | foundation laying

Classroom extension | wall demolition

Classroom extension | support beam addition

Classroom extension | demolition and plastering

Classroom extension | completion

Classroom extension | completion

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor


Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

Construction process of the second floor

COMPLETION